The Impact of Overlapping Phases in EPCC Projects on the Accuracy of 4D BIM (Time) and 5D BIM (Cost): A Literature Review

  • Nadiatul Huliyah Master of Civil Engineering Study Program, Faculty of Civil Engineering and Planning, Universitas Trisakti, Jakarta, Indonesia
  • Bambang Endro Yuwono Master of Civil Engineering Study Program, Faculty of Civil Engineering and Planning, Universitas Trisakti, Jakarta, Indonesia
Keywords: EPCC, Phase Overlap, 4D BIM, 5D BIM, Time, Cost

Abstract

Engineering, Procurement, Construction, and Commissioning (EPCC) projects often apply overlapping phases to accelerate project completion. This strategy allows procurement, construction, or commissioning to start before the preceding phase is fully completed. However, design, material, schedule, and cost information may continue to change and affect the accuracy of 4D and 5D Building Information Modeling (BIM). This study explains the effect of EPCC phase overlap on the time accuracy of 4D BIM and the cost accuracy of 5D BIM and describes the role of BIM in project control. A literature review was conducted using 38 journal articles covering fast-track construction, 4D BIM, 5D BIM, scheduling, procurement, quantity take-off, interoperability, and cost control. The findings show that overlap can reduce BIM accuracy when design changes, procurement status, field progress, and cost information are not updated promptly. The accuracy of 4D BIM is affected in work sequence, activity relationships, duration, progress, and completion time. The accuracy of 5D BIM is affected in quantities, prices, rework costs, scope changes, and final cost forecasts. Nevertheless, BIM remains important because it enables project teams to identify the time and cost consequences of changes more quickly. BIM accuracy can be maintained through regular model updates, consistent project data, integration of models with schedule and cost information, and coordination among EPCC phases.

References

Alathamneh, S., Collins, W., & Azhar, S. (2024). BIM-based quantity takeoff: Current state and future opportunities. Automation in Construction, 165, 105549. https://doi.org/10.1016/j.autcon.2024.105549

Arifuddin, R., & Abdurrahman, M. A. (2026). Analysis of the Delay Risk of the Engineering, Procurement, Construction, and Commissioning (EPCC) Phases in Oil and Gas Industry Projects. Engineering, Technology & Applied Science Research, 16(1), 32015-32023. https://doi.org/10.48084/etasr.13969

Azhar, S. (2011). Building information modeling (BIM): Trends, benefits, risks, and challenges for the AEC industry. Leadership and Management in Engineering, 11(3), 241–252. https://doi.org/10.1061/(ASCE)LM.1943-5630.0000127

Barlish, K., & Sullivan, K. (2012). How to measure the benefits of BIM—A case study approach. Automation in Construction, 24, 149–159. https://doi.org/10.1016/j.autcon.2012.02.008

Boton, C. (2018). Supporting constructability analysis meetings with immersive virtual reality-based collaborative BIM 4D simulation. Automation in Construction, 96, 1–15. https://doi.org/10.1016/j.autcon.2018.08.020

Bryde, D., Broquetas, M., & Volm, J. M. (2013). The project benefits of building information modelling (BIM). International Journal of Project Management, 31(7), 971–980. https://doi.org/10.1016/j.ijproman.2012.12.001

Cao, D., Wang, G., Li, H., Skitmore, M., Huang, T., & Zhang, W. (2015). Practices and effectiveness of building information modelling in construction projects in China. Automation in Construction, 49, 113–122. https://doi.org/10.1016/j.autcon.2014.10.014

Cassandro, J., Mirarchi, C., & Pavan, A. (2025). A comprehensive literature review of 5D building information modelling using latent Dirichlet allocation analysis. Construction Innovation. https://doi.org/10.1108/CI-07-2024-0209

Doukari, O., Seck, B., & Greenwood, D. (2022). The creation of construction schedules in 4D BIM: A comparison of conventional and automated approaches. Buildings, 12(8), 1145. https://doi.org/10.3390/buildings12081145

Garrido Martins, C., Bogus, S. M., & Valentin, V. (2023). Perceptions of construction risks due to fast-track activity overlapping. Eng, 4(4), 2879–2895. https://doi.org/10.3390/eng4040162

Gledson, B. J., & Greenwood, D. J. (2016). Surveying the extent and use of 4D BIM in the UK. Journal of Information Technology in Construction, 21, 57–71.

Gledson, B. J., & Greenwood, D. J. (2017). The adoption of 4D BIM in the UK construction industry: An innovation diffusion approach. Engineering, Construction and Architectural Management, 24(6), 950–967. https://doi.org/10.1108/ECAM-03-2016-0066

Hartmann, T., Gao, J., & Fischer, M. (2008). Areas of application for 3D and 4D models on construction projects. Journal of Construction Engineering and Management, 134(10), 776–785. https://doi.org/10.1061/(ASCE)0733-9364(2008)134:10(776)

Heesom, D., & Mahdjoubi, L. (2004). Trends of 4D CAD applications for construction planning. Construction Management and Economics, 22(2), 171–182. https://doi.org/10.1080/0144619042000201376

Hussain, O. A. I., Moehler, R. C., Walsh, S. D. C., & Ahiaga-Dagbui, D. D. (2024). Minimizing cost overrun in rail projects through 5D-BIM: A conceptual governance framework. Buildings, 14(2), 478. https://doi.org/10.3390/buildings14020478

Jaafar, Z., & Zainuddin, M. I. (2020, November). Successful Project Delivery Through Effective and Well–Timed Operation and Maintenance Involvement During Project Life–cycle. In Abu Dhabi International Petroleum Exhibition and Conference (p. D031S096R003). SPE. https://doi.org/10.2118/203124-MS

Khosakitchalert, C., Yabuki, N., & Fukuda, T. (2020). Development of BIM-based quantity takeoff for light-gauge steel wall framing systems. Journal of Information Technology in Construction, 25, 522–544. https://doi.org/10.36680/j.itcon.2020.030

Kim, C., Son, H., & Kim, C. (2013). Automated construction progress measurement using a 4D building information model and 3D data. Automation in construction, 31, 75-82. https://doi.org/10.1016/j.autcon.2012.11.041

Koo, B., & Fischer, M. (2000). Feasibility study of 4D CAD in commercial construction. Journal of Construction Engineering and Management, 126(4), 251–260. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:4(251)

Laakso, M., & Kiviniemi, A. (2012). The IFC standard—A review of history, development, and standardization. Journal of Information Technology in Construction, 17, 134–161.

Lu, Q., Won, J., & Cheng, J. C. P. (2016). A financial decision making framework for construction projects based on 5D Building Information Modeling (BIM). International Journal of Project Management, 34(1), 3–21. https://doi.org/10.1016/j.ijproman.2015.09.004

Miettinen, R., & Paavola, S. (2014). Beyond the BIM utopia: Approaches to the development and implementation of building information modeling. Automation in Construction, 43, 84–91. https://doi.org/10.1016/j.autcon.2014.03.009

Monteiro, A., & Martins, J. P. (2013). A survey on modeling guidelines for quantity takeoff-oriented BIM-based design. Automation in Construction, 35, 238–253. https://doi.org/10.1016/j.autcon.2013.05.005

Noardo, F., Krijnen, T., Arroyo Ohori, K., Biljecki, F., Ellul, C., Harrie, L., Eriksson, H., Polia, L., Salheb, N., Tauscher, H., van Liempt, J., Goerne, H., Hintz, D., Kaiser, T., Leoni, C., Warchol, A., & Stoter, J. (2021). Reference study of IFC software support: The GeoBIM benchmark 2019—Part I. Transactions in GIS, 25(2), 805–841. https://doi.org/10.1111/tgis.12709

Page, M. J., McKenzie, J. E., Bossuyt, P. M., Boutron, I., Hoffmann, T. C., Mulrow, C. D., et al. (2021). The PRISMA 2020 statement: An updated guideline for reporting systematic reviews. BMJ, 372, n71. https://doi.org/10.1136/bmj.n71

Pauwels, P., Zhang, S., & Lee, Y.-C. (2017). Semantic web technologies in AEC industry: A literature overview. Automation in Construction, 73, 145–165. https://doi.org/10.1016/j.autcon.2016.10.003

Peña-Mora, F., & Li, M. (2001). Dynamic planning and control methodology for design/build fast-track construction projects. Journal of Construction Engineering and Management, 127(1), 1–17. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:1(1)

Peña-Mora, F., & Park, M. (2001). Dynamic planning for fast-tracking building construction projects. Journal of Construction Engineering and Management, 127(6), 445–456. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:6(445)

Pishdad, P., & Onungwa, I. O. (2024). Analysis of 5D BIM for cost estimation, cost control and payments. Journal of Information Technology in Construction, 29, 525–548. https://doi.org/10.36680/j.itcon.2024.024

Prasetya, R. B. (2026). Risk Management in Engineering, Procurement, and Construction (EPC) Projects for Green Ammonia Using Renewable Energy. IPTEK The Journal for Technology and Science, 37(1), 68-91. https://doi.org/10.12962/j20882033.v37i1.9261

Rehman, I. U., Mazher, K. M., & Wuni, I. Y. (2025). Systematic review of 4D BIM benefits in construction projects. Results in Engineering, 28, 107091. https://doi.org/10.1016/j.rineng.2025.107091

Sacks, R., Koskela, L., Dave, B. A., & Owen, R. (2010). Interaction of lean and building information modeling in construction. Journal of Construction Engineering and Management, 136(9), 968–980. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000203

Smith, P. (2014). BIM & the 5D project cost manager. Procedia - Social and Behavioral Sciences, 119, 475–484. https://doi.org/10.1016/j.sbspro.2014.03.053

Staub-French, S., & Khanzode, A. (2007). 3D and 4D modeling for design and construction coordination: Issues and lessons learned. Journal of Information Technology in Construction, 12, 381–407.

Succar, B. (2009). Building information modelling framework: A research and delivery foundation for industry stakeholders. Automation in Construction, 18(3), 357–375. https://doi.org/10.1016/j.autcon.2008.10.003

Turkan, Y., Bosché, F., Haas, C. T., & Haas, R. (2012). Automated progress tracking using 4D schedule and 3D sensing technologies. Automation in Construction, 22, 414–421. https://doi.org/10.1016/j.autcon.2011.10.003

Vigneault, M. A., Boton, C., Chong, H.-Y., & Cooper-Cooke, B. (2020). An innovative framework of 5D BIM solutions for construction cost management: A systematic review. Archives of Computational Methods in Engineering, 27(4), 1013–1030. https://doi.org/10.1007/s11831-019-09341-z

Volk, R., Stengel, J., & Schultmann, F. (2014). Building Information Modeling (BIM) for existing buildings—Literature review and future needs. Automation in Construction, 38, 109–127. https://doi.org/10.1016/j.autcon.2013.10.023

Wang, Q., & Wang, J. (2022). Research on key risk factors and risk transmission path of procurement in international engineering procurement construction project. Buildings, 12(5), 534. https://doi.org/10.3390/buildings12050534

Zhang, C., & Arditi, D. (2013). Automated progress control using laser scanning technology. Automation in Construction, 36, 108–116. https://doi.org/10.1016/j.autcon.2013.08.012

Zhao, X. (2017). A scientometric review of global BIM research: Analysis and visualization. Automation in Construction, 80, 37–47. https://doi.org/10.1016/j.autcon.2017.04.002