Analysis of Working Time Measurement and Incentives Work to Increase Shoe Upper Production at CV. Esa Kalen Jaya

  • Putri Olivia Agustin The National Development University "Veteran" of East Java, Industrial Engineering, Surabaya, Indonesia
  • Rusindiyanto The National Development University "Veteran" of East Java, Industrial Engineering, Surabaya, Indonesia
Keywords: Productivity, Output Standard, Stopwatch Time Study, Piecework Plan

Abstract

As time goes by, competition in the industrial world is increasing, every company is required to be able to compete with other companies. CV.Esa Kalen Jaya is a company that produces semi-finished goods, namely shoe uppers. Where there are obstacles in the form of not being able to fulfill the production targets that have been determined by the company which results in the company's productivity not being optimal. This research was conducted to calculate standard production time through direct observation using a stopwatch time study as well as improving the regulation of the number of working hours and providing work incentives using the piecework plan method. as an effort to increase company productivity.. Results obtained. The standard output obtained is 4588.48 units/month. And after increasing the number of production working hours to 8 working hours, the results were 5,234 units/month, which means the production target has been achieved. And based on the calculation of incentives that the company will provide in standard hourly wages, namely IDR 7,051.41/hour. It can be concluded that by determining the standard production time and determining the number of working hours, the production results have achieved the set production targets.

References

Afiani, R., & Pujotomo, D. (2017). Penentuan Waktu Baku Dengan Metode Stopwatch Time Study Studi Kasus Cv. Mans Group. Industrial Engineering Online Journal, 6(1).

Alwi, A. (2022). Analisis Pencapaian Target Produksi Kertas untuk Peningkatan Efisiensi Produksi di PT OKI Pulp and Paper di Sungai Baung Ogan Komering Ilir. Jurnal Multidisiplin Dehasen (MUDE), 1(2), 20-26. https://doi.org/10.37676/mude.v1i2.2061

Asarela, S., & Sari, R. P. (2023). Analisis Pengukuran Kerja Menentukan Waktu Baku Menggunakan Metode Jam Henti Terhadap Operator Persiapan Komponen ( Studi Kasus : PT XYZ ). Journal Serambi Engineering, VIII(3), 6479–6486.

Douw, N. I., Maarif, M. S., & Baga, L. M. (2021). Peningkatan Produktivitas Kerja Karyawan Development Di Tambang Bawah Tanah Dmlz (Deep Mill Level Zone) Pt Freeport Indonesia. Jurnal Aplikasi Bisnis dan Manajemen (JABM), 7(2), 316-316. https://doi.org/10.17358/jabm.7.2.316

Fardiansyah, I., Widodo, T., & Anggraini, W. (2022). Pengukuran Waktu Kerja Dengan Metode Time Motion Study Untuk Meningkatkan Produktivitas Kerja Produksi Greenware (Studi kasus: PT XYZ). Journal Industrial Manufacturing, 7(2), 85-96. http://dx.doi.org/10.31000/jim.v7i2.6924

Farida, I., & Setiawan, D. (2022). Business strategies and competitive advantage: the role of performance and innovation. Journal of Open Innovation: Technology, Market, and Complexity, 8(3), 163. https://doi.org/10.3390/joitmc8030163

Fragapane, G., Ivanov, D., Peron, M., Sgarbossa, F., & Strandhagen, J. O. (2022). Increasing flexibility and productivity in Industry 4.0 production networks with autonomous mobile robots and smart intralogistics. Annals of operations research, 308(1), 125-143. https://doi.org/10.1007/s10479-020-03526-7

Juwardi, U., Adnan, S. R., Rachman, T., Amperajaya, M. D., Erni, N., Rasjidin, R., & Fajrah, M. C. (2023). Perhitungan Waktu Baku Dan Penentuan Produktivitas Pada Pengerjaan Pembersihan Kaca Gedung X. Jurnal Konversi Energi dan Manufaktur, 67-77.

Kayatun, S. N., Tajuddin, T., Masniar, M., & Sodikin, M. (2022). Hubungan Kepuasan Kerja Dengan Motivasi Kerja Karyawan. Metode: Jurnal Teknik Industri, 8(1), 31-40. https://doi.org/10.33506/mt.v8i1.1697

Kristoffersen, E., Blomsma, F., Mikalef, P., & Li, J. (2020). The smart circular economy: A digital-enabled circular strategies framework for manufacturing companies. Journal of business research, 120, 241-261. https://doi.org/10.1016/j.jbusres.2020.07.044

Palange, A., & Dhatrak, P. (2021). Lean manufacturing a vital tool to enhance productivity in manufacturing. Materials Today: Proceedings, 46, 729-736. https://doi.org/10.1016/j.matpr.2020.12.193

Putra, M. R., & Gupron, G. (2020). Employee performance models: Competence, compensation and motivation (Human resources literature review study). Dinasti International Journal of Education Management And Social Science, 2(1), 185-198. https://doi.org/10.31933/dijemss.v2i1.629

Qomariah, N., Nyoman, N., & Martini, P. (2022). The Influence of Leadership Style, Work Incentives and Work Motivation on the Employees Performance of Regional Revenue Agency. Journal of Economics, Finance and Management Studies, 5(07), 1942-1954.

Rachmawati, D. (2021). Analisis Pemberian Insentif Terhadap Kinerja Karyawan Di Departemen Penjualan Pg Kebon Agung Malang. Journal Koperasi Dan Manajemen, 2(02), 7-17.

Sitorus, E., & Alfath, N. (2017). Optimasi jumlah tenaga kerja berdasarkan waktu standard. Jurnal Sistem Teknik Industri, 19(2), 10-14. https://doi.org/10.32734/jsti.v19i2.368

Syafitri, A., Nurbaiti, N., & Diana, D. (2022). Peningkatan Produktivitas Tenaga Kerja Melalui Program Insentif Pada PT. Kirana Windu Surulangun Rawas. Jurnal Sistem Informasi, Akuntansi & Manajemen), 2(2), 254-263.

Published
2024-06-25
How to Cite
Agustin, P. O., & Rusindiyanto, R. (2024). Analysis of Working Time Measurement and Incentives Work to Increase Shoe Upper Production at CV. Esa Kalen Jaya. Journal La Multiapp, 5(2), 120-130. https://doi.org/10.37899/journallamultiapp.v5i2.1293